LRT3 Shah Alam Line Opening postponed to the end of the year? – Paultan.org

LRT3 Shah Alam Line Opening postponed to the end of the year? – Paultan.org

2 minutes, 7 seconds Read

The opening of the LRT3 Shah Alam Line can be postponed to the end of2025, as a report by The star Is to believe. The English -language daily seeing a memo in which Prasarana Malaysia President and CEO Amir Hamdan de Hoop expressed that there would be no more delays, so that the project can be opened for service in December.

“God wants, the project will be a critical phase called the error -free run (FFR) on 25 August. We pray that this test will go smoothly as planned without more delays, so that we can complete the project on time for the launch,” Amir said.

Transport Minister Anthony Loke said on July 30 in a written parliamentary answer that LRT3 was completed 99.21% from July 10. However, Prasarana said on social media on 25 July that the trains would be tested until October 31 to October 31 “Until October 31, one month after the targeted opening date of 30 September. This message was changed to delete the date afterwards The star Ran a story of 4 August about the delay.

LRT3 Shah Alam Line Opening postponed to the end of the year?

The 37 km line contains 25 stations from Bandar Utama to Johan Setia, with exchanges in Bandar Utama (Kajang Mar) and Glenmarie (Kelana Jaya Lrt). It is subject to various changes since the 2018 government change, especially to do with Down-Scaling and cost-saving.

The MRCB-George Kent JV was appointed project delivery partner (PDP) in 2015. After leaving the PDP model for a gymnastics contract with a fixed price in November 2018, the contractor Setia Utama LRT3 was renamed. The star Understands that the FFR trips this year were caused by various problems, in particular to the integration of signaling, communication and electrification.

Later this week the first of the 22 trains must complete 4,000 km of testing without errors; The rest must each do at least 2,000 km. Each train must also be able to travel in an hour or less in an hour or less with a maximum of six minutes of progress, which is needed at 18,630 passengers per hour per direction.

Do you want to sell your car? Sell ​​it with Auto.


#LRT3 #Shah #Alam #Line #Opening #postponed #year #Paultan.org

Similar Posts

Leave a Reply

Your email address will not be published. Required fields are marked *